Four flow models are available in Power Automate so you can create Finalcad observations and forms when a task is created in Microsoft Planner, and vice versa.
Add an observation when a project task is created
Add a form when a project task is created
Step | Action objective | Fields to fill |
When a new task is created | Select the Planner plan from which you want to retrieve tasks. |
|
List buckets | Select the Planner plan from which you want to retrieve tasks. |
|
Setup - Project | Select the Finalcad project in which elements will be created |
|
Project - Create observation | Choose the module and template of the element | For observations
For forms
|
Add a project task when an observation is created
Add a project task when a form is created
Step | Action objective | Fields to fill |
Trigger - Observation/Form created | Select the Finalcad project from which you want to retrieve elements |
|
Create a task | Select the Planner plan in which you want to create tasks. |
|
Create a task simple | Select the Planner plan in which you want to create tasks. |
|
Vous pouvez effectuer dâautres modifications au flux si vous le souhaitez.
Lorsque votre flux est prĂȘt :
Cliquez sur âEnregistrerâ puis âTesterâ
Cliquez sur le bouton pour tester le flux âManuellementâ
Cliquez sur le bouton âRun flowâ
Si le flux a bien fonctionné :
le message âYour flow ran successfully sâaffiche.â
toutes les étapes du flux apparaissent comme validées